  • Work begins on Upper Gilchrist Road

  • October 14, 2009

MOUNT VERNON — The water problems creating the breakup of a section of Upper Gilchrist Road are being addressed with a $212,000 grant to Monroe Township from the Ohio Public Works Commission. Work is under way by Small’s Sand and Gravel Co. to bury drainage tile under the road.

The 4-inch perforated plastic tile is placed in a trench 24 inches under the road surface; the trench is then filled with gravel, allowing water to flow through the gravel and into the tile. A total of 11,188 feet of the tile is to be installed, and is expected to be completed this week.

To prepare for the new paving on the surface, the old pavement will be rototilled. The new road surface will be asphalt with a chip-and-stone seal on top. The grant money covers a 1.1-mile section of road.

  • E-mail Story
  • Twitter
  • FeedBurner
  • RSS Feed
  • Advertisement

    Union National Mortgage - 1650 Coshocton Avenue

     

    Sponsored Links
       

    © Copyright 2012 Progressive Communications. All rights reserved. This material may not be published, broadcast, rewritten, or redistributed, without the expressed permission of Progressive Communications.

    · Return to top

    Sections:
    Local   Sports   Classifieds   Obituaries   Weather
    Online:
    Search   Site Map   Posting Policy   Privacy Policy   E-edition   Contact Us   Staff
    Services:
    Subscribe   Purchase Photos   Advertise
    Submit:
    Events   Anniversary   Engagement Form   Wedding   Suggest a story   Roll Call   Clubs   4-H   Vacation   Recipe   Problems
    Social:
    Twitter   Facebook   YouTube

    © Progressive Communications Corporation.

    Phone: (740) 397 5333 or 1-800-772-5333 (Toll Free in Ohio)